Free Project Status Report Template

Share progress clearly with this free project status report template. It follows a proven project status report format: summary, milestones, risks, budget and next steps. Free download in Excel and PDF.

  • Free download
  • Excel (.xlsx)
  • PDF
  • One-page format
A one-page project status report, filled in with an example project.

A one-page project status report, filled in with an example project.

Enlarged view: Free project status report template with overall status, summary, milestones, budget, risks and next steps

Preview: milestones in the status report

The milestone table shows what is complete, on track or at risk, with a comment for each.

Project status report template milestone table with example rows
MilestoneDue dateStatus% completeComments
Design approval14-11-2026Complete100%Signed off by client
Materials ordered20-11-2026On track50%2 of 4 purchase orders raised
Phase 1 delivery15-12-2026At risk10%Supplier delay of one week
Final handover22-12-2026Not started0%—
Format

Project status report format

A good project status report format fits on one page and answers one question first: is the project on track? This template opens with the project name, reporting period, the person preparing it and an overall status of On track, At risk or Off track. A short summary follows in two or three sentences.

Below that come four blocks: milestones with due date, status, % complete and comments; budget with contract value, invoiced, still to bill, estimated cost and expected margin; risks and issues with impact, owner and action; and next steps. The same order every week makes reports quick to write and quick to read.

Contents

What to include in a project status report

Keep it factual and short. Each block answers a question your reader will ask.

  • Overall status: is the project on track?
  • Summary: what happened this period?
  • Milestones: what is done, due or late?
  • Budget: how much is billed and how much is left?
  • Risks and issues: what could go wrong, and who is acting?
  • Next steps: what will happen before the next report?
Frequency

How often to send a project status report

Weekly works for most projects; fortnightly can be enough for long, steady projects. Send it on the same day each time so your client and management know when to expect it. If the overall status changes to At risk or Off track, do not wait for the next report: tell the people affected straight away and use the report to record the action taken.

Free download

Free download: status report template in Excel and PDF

Download the Excel version to fill in on your computer, or the PDF to print. Both are free, with no sign-up. To keep the milestone list up to date between reports, use the free project management Excel template.

Next step

Automate project status reports in Catalystk

Most of this report already exists in free project management software. Catalystk's project dashboard shows contract value, invoiced and still to bill, work done, timeline and overdue milestones for every project, and you can download the project in Excel and PDF whenever a report is due. To see estimated cost and margin as well, link a cost estimate with free project cost tracking software.

Free download in Excel and PDF, no sign-up.

Project Status Report Template: frequently asked questions

Is the project status report template free?

Yes. It is a free download in Excel and PDF, with no sign-up.

What is the best project status report format?

One page: overall status, a short summary, milestones, budget, risks and issues, and next steps, in the same order every time.

How often should I send a project status report?

Weekly for most projects, or fortnightly for long, steady ones. Report a change to At risk or Off track straight away.

Can I use it as a weekly status report template?

Yes. Set the reporting period to one week and update the milestones, budget and risks each week.

Can software create the status report for me?

Catalystk's free project dashboard shows progress, billing and overdue milestones for every project, and you can download it in Excel and PDF.

Related free tools and guides

Ready to run your business on one platform?

Join thousands of growing businesses using Catalystk. Set up in minutes — free forever, no credit card required.

WhatsApp